Network Modernization Project

Transforming Connectivity at Mines

Mines has launched the Network Modernization Project, a multi-year initiative to upgrade the campus network. This project aims to advance academic and research excellence by delivering faster, more reliable connections, expanding campus-wide wireless coverage, and increasing network capacity. The enhanced infrastructure will also strengthen network security and better support the evolving needs of our campus community.

Upgrades will be implemented building by building throughout 2025 and 2026. As your building’s installation date approaches, you’ll receive an email with all the details you’ll need to prepare.

Tentative Building Schedule

The building schedule below provides a tentative timeline for installations. Please note that these dates are subject to change based on project requirements and unforeseen circumstances.

 

Completed Date Building(s)
  May 2024 Football: Marv Kay Stadium
July 2024 Pilot: 1600 Jackson, Veterans Resource Center, Kappa Alpha Theta house
January 2025 Phase 1: Athletic Complex Buildings
February-April 2025

Phase 2: Administration/Academic Buildings

  • February: Berthoud Hall
  • March: Guggenheim Hall, CTLM, Marquez Hall, 
  • April: Alderson Hall, 1704 Illinois, 1700 Illinois, USGS, Unit Operations Lab
May-August 2025

Phase 3: Residence Hall Buildings

  • May: Elm Hall, 1750 Jackson St Hall  
  • June:  Morgan Hall, Bradford Hall, Randall Hall, Thomas Hall, Maple Hall  
  • July: Coolbaugh House, University Honors & Scholars Program (1706 Illinois), WISEM (1710 Illinois), Weaver Towers East & West  
  • August:  Spruce Hall
  August-December 2025

Phase 4: 13th & 14th Street Buildings 

  • August: [Completed] CoorsTek 
  • September: [Completed] Stratton Hall, Chauvenet Hall, Hill Hall
  • October: [Completed] Engineering Hall, Engineering Hall Annex,  Coolbaugh Hall, Arthur Lakes Library, Volk Gymnasium, Steinhauer Field House
  • November: [Completed] General Research Lab (GRL), Aramco xWorks, EMI Drilling Laboratory, GRL Annex
  • December: [Completed] Student Recreation Center
  January 2026

Phase 5: Green Center & Brown Hall 

  • January: Green Center, 812 16th Street, Sigma Nu & FM Grounds House, President’s Residence, Brown Hall
  February-March 2026

Phase 6: West Campus & 19th Street Buildings 

  • February: Starzer Welcome Center, Beck Venture Center, McNeil Hall, Labriola Innovation Hub
  • March:  W. Lloyd Wright Student Wellness Center, Disability Support Services (1225 17th Street), Aspen Hall (1850 W. Campus), Pi Phi Sorority (1500 W. Campus), Alpha Phi Sorority (1550 W. Campus), Sigma Kappa Sorority (1600 W. Campus), Phi Gamma Delta Fraternity,  Ben H. Parker Student Center, Central Storage & Receiving, Music Program, ROTC, ROTC-Trailer
  April-May 2026

Phase 7: Moly Building & Mines Park 

  • April: Moly Building, Mines Park Wastewater Treatment Plant, Aqwatech, Survey Field Office, Shop 1, Shop 2, Mines Park 2001, Mines Park 1903, Mines Park 1905, Mines Park 1907, Mines Park 1909, Mines Park 1911
  • May: Mines Park 1913, Mines Park 2003, Mines Park 2005, Mines Park 2007, Mines Park 2009, Mines Park 2011, Mines Park 2013, Mines Park 2015, Mines Park 2017, Mines Park 2019, Mines Park 2021, Mines Park 2023, Mines Park 2025, Mines Park 2027
  May-June 2026 Phase 8: Edgar Mine & Heating Plant

More Information

Project Team

Executive Sponsor: Andrew Moore

Sponsor: Matt Ketterling

Senior Project Manager: Joan L. Terrill

Technical Lead: George Hendricks